Rewiring projects

Millikan rewire _DONE_

  • rewiring - completed
  • testing - completed
  • auditing - completed
  • cleanup - completed

Seaver Theater rewire

  • rewiring - completed
  • testing - completed found two problem outlets fixed during testing
  • install new switch - completed
  • auditing - completed
  • cleanup - office space completed classroom space unknown

Rembrandt rewiring

  • rewiring - in process (ETA 8/16/05)
  • testing - incompleted
  • auditing - incompleted
  • cleanup - incompleted

Sumner House rewiring

  • Fibre optic cable installation - completed
  • Data Outlet installation - pending meeting with Don on locations
  • testing - incompleted
  • auditing - incompleted
  • installation new switch - pending hardware arrival
  • cleanup - incompleted

Wig Dormitory renovation

  • Install new wiring in construction - completed
  • Install addtional wiring and jacks in dorm rooms 120,111,113 - completed
  • Relocation of patch panel - incompleted
  • Retermination of all data in new patch panel - completed
  • Auditing - drawing provided by Primary Cableworks
  • Repatching - pending (eta to start 8/17/05)
  • cleanup - incompleted

Gibson Hall conversion

  • Wiring - inprogress (ETA to complete 8/18/05)
  • testing - pending
  • auditing - information to be provided by Primary Cablework on completion of testing
  • patching - pending (ETA 8/19/05)
  • cleanup - incompleted
 