Rewiring projects
Millikan rewire
_DONE_
rewiring - completed
testing - completed
auditing - completed
cleanup - completed
Seaver Theater rewire
rewiring - completed
testing - completed found two problem outlets fixed during testing
install new switch - completed
auditing - completed
cleanup - office space completed classroom space unknown
Rembrandt rewiring
rewiring - in process (ETA 8/16/05)
testing - incompleted
auditing - incompleted
cleanup - incompleted
Sumner House rewiring
Fibre optic cable installation - completed
Data Outlet installation - pending meeting with Don on locations
testing - incompleted
auditing - incompleted
installation new switch - pending hardware arrival
cleanup - incompleted
Wig Dormitory renovation
Install new wiring in construction - completed
Install addtional wiring and jacks in dorm rooms 120,111,113 - completed
Relocation of patch panel - incompleted
Retermination of all data in new patch panel - completed
Auditing - drawing provided by Primary Cableworks
Repatching - pending (eta to start 8/17/05)
cleanup - incompleted
Gibson Hall conversion
Wiring - inprogress (ETA to complete 8/18/05)
testing - pending
auditing - information to be provided by Primary Cablework on completion of testing
patching - pending (ETA 8/19/05)
cleanup - incompleted
Main
Log In
or
Register
Main Web
Users
Groups
Index
Search
Changes
Notifications
Statistics
Preferences
Webs
FAQ
Main
Copyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki?
Send feedback